Tuesday, October 29, 2013

Vanderbilt Country Club Fitness Center's Interior Moving Along

BCBE Construction is moving along on the interior of Vanderbilt Country Club's new Fitness Center and continues with the renovations of the Pro Shop and Activities Building/Clubhouse in Naples, Florida. 

Get the latest update on what is happening now and what is coming up with the Fitness Center and the Clubhouse/Activities Building.  

Fitness Center (This Week):
  • Installing Glass in Frames 
  • Delivery of AC Units
  • Install Stucco Beads
  • Complete Metal Framing Installation
  • HVAC, Electric, Plumbing Rough 
  • Installing All Plywood Backing for Televisions
  • Rough Inspections 

Looking Ahead:
  • Install Drywall 
  • Install Wall Insulation
  • Stucco
  • Frame Fire Rated Ceiling
  • Mechanical Electrical Plumbing Rough Inspections 
  • Framing Inspection 







Activities Building (This Week):
  • Re-roofing to Start 
  • Roof Trusses and Sheathing is Complete & Inspected
  • Dry In Roof
Looking Ahead:
  • Interior Framing
  • Window Install
  • Mechanical Electrical Plumbing Rough 

Clubhouse (This Week):
  • Demolition
  • Site Work and Removals

Looking Ahead:
  • Interior Framing
  • Concrete Formwork, Flatwork and Masonry Install
  • Underground Utilities






Please visit BCBE Construction's website at www.bcbe.com for continuous updates on the progress of Vanderbilt Country Club's renovations.