Get the latest update on what is happening now and what is coming up with the Fitness Center and the Clubhouse/Activities Building.
Fitness Center (This Week):
- Installing Glass in Frames
- Delivery of AC Units
- Install Stucco Beads
- Complete Metal Framing Installation
- HVAC, Electric, Plumbing Rough
- Installing All Plywood Backing for Televisions
- Rough Inspections
Looking Ahead:
- Install Drywall
- Install Wall Insulation
- Stucco
- Frame Fire Rated Ceiling
- Mechanical Electrical Plumbing Rough Inspections
- Framing Inspection
Activities Building (This Week):
- Re-roofing to Start
- Roof Trusses and Sheathing is Complete & Inspected
- Dry In Roof
Looking Ahead:
- Interior Framing
- Window Install
- Mechanical Electrical Plumbing Rough
Clubhouse (This Week):
- Demolition
- Site Work and Removals
Looking Ahead:
- Interior Framing
- Concrete Formwork, Flatwork and Masonry Install
- Underground Utilities
Please visit BCBE Construction's website at www.bcbe.com for continuous updates on the progress of Vanderbilt Country Club's renovations.